SHORE VISION 2035 - SUBMISSION OF PRELIMINARY EXCESS INFRASTRUCTURE REPORT:
RAAUZYUW RUEWMCS0000 2202153-UUUU--RUCRNAD ZNR UUUUU R 072153Z AUG 08 FM CNO WASHINGTON DC//DNS// TO NAVADMIN BT UNCLAS NAVADMIN 216/08 MSGID/NAVADMIN/CNO WASHINGTON DC/DNS/JUL// SUBJ/SHORE VISION 2035 - SUBMISSION OF PRELIMINARY EXCESS INFRASTRUCTURE REPORT// POC/MS. VERA EMBICK/CNIC N4 STAFF/EMAIL:VERA.EMBICK@NAVY.MIL/COMM:202- 433-4465.// REF/A/GENADMIN/CNO WASHINGTON DC/181603ZJUN2008/NOTAL// AMPN/REF A IS CNO PERSONAL FOR - SHORE VISION 2035.// RMKS/1. AS DELINEATED IN REF A, CHIEF OF NAVAL OPERATIONS (CNO) DIRECTED A "FULL COURT PRESS TO QUICKLY DRIVE OUR NAVY TO A MORE EFFECTIVE, EFFICIENT GLOBAL SHORE INFRASTRUCTURE." TO THIS END, IT IS IMPERATIVE THAT WE REDUCE OUR SHORE FOOTPRINT, WHEREVER PRACTICAL. CNO DIRECTED EACH WARFARE ENTERPRISE AND PROVIDER (WE/P) TO REVISIT THEIR GLOBAL SHORE INFRASTRUCTURE PLAN (GSIP) AND IDENTIFY CRITICAL INFRASTRUCTURE REQUIREMENTS (BASIC PLUS MINIMAL SURGE) AND EXCESS INFRASTRUCTURE (EXCESS SURGE). 2. COMMANDER, NAVY INSTALLATIONS COMMAND (CNIC), AS NAVY'S "SHORE INTEGRATOR," WILL COORDINATE THE ACTION DIRECTED IN PARA 5 OF REF A, WHICH REQUIRES EACH WE/P TO IDENTIFY THEIR PRELIMINARY EXCESS FACILITY INFRASTRUCTURE, AND A SUBSEQUENT REPORT TO THE DEPUTY CHIEF OF NAVAL OPERATIONS, FLEET READINESS AND LOGISTICS (CNO N4) WITHIN THE NEXT 60 DAYS. INTENT OF THE REVIEW IS FOR EACH WE/P TO LOOK CLOSELY AT CURRENT AND NEAR TERM OPERATIONS AND BUSINESS PROCESSES THAT CAN BE CHANGED TO ELIMINATE EXCESS FACILITIES AND SHORE FOOTPRINT, REDUCE THE CARRYING COST OF TODAY'S INFRASTRUCTURE, AND QUICKLY DRIVE OUR NAVY TO A MORE EFFECTIVE, EFFICIENT GLOBAL SHORE INFRASTRUCTURE DELIVERED AT LOWEST LIFE-CYCLE COST. 3. GUIDANCE FOR REPORTING EXCESS INFRASTRUCTURE: A. EACH WE/P WILL IDENTIFY THEIR BASELINE SHORE INFRASTRUCTURE FACILITY REQUIREMENTS ACROSS THEIR RESPECTIVE ENTERPRISE/DOMAIN OVER THE NEXT 5 YEAR PERIOD AND IDENTIFY OPPORTUNITIES FOR INFRASTRUCTURE REDUCTION. WE/P REVIEW SHOULD TAKE INTO CONSIDERATION PROSPECTIVE CHANGES IN CONOPS, FORCE LAYDOWN, SURGE REQUIREMENTS, BUSINESS PROCESSES, AND OTHER EXISTING PLANS AND COMPARE THOSE REQUIREMENTS TO THE INFRASTRUCTURE THAT EACH USES TODAY. IT IS ENVISIONED THAT YOUR RESPECTIVE GSIP WOULD BE USED FOR THIS ASSESSMENT, WITH UPDATES AS YOU DEEM NECESSARY. TEMPLATE AND INSTRUCTIONS ARE PROVIDED IN A ZIP FILE THAT CAN BE DOWNLOADED FROM THIS LINK (HTTPS://WWW.CNIC.NAVY.MIL/NAVYCNI/GROUPS/PUBLIC/DOCUMENTS/DOCUMENT/INF RASTRUCTURE EXCESSSURGE.ZIP). (1) ALL FACILITIES, FUNDED OR OPERATED BY OPERATIONS AND MAINTENANCE NAVY, OPERATIONS AND MAINTENANCE NAVY RESERVE, NAVY WORKING CAPITAL FUND AND RESEARCH, DEVELOPMENT, TEST AND EVALUATION ACTIVITIES, ARE TO BE INCLUDED IN THIS ANALYSIS. (2) WHILE CNIC HQ AND REGIONAL ENGINEERS CAN PROVIDE TECHNICAL ADVICE TO THE WE/P'S AS NEEDED, THE FINAL PRODUCT FROM THIS EVOLUTION BELONGS TO THE RESPECTIVE WE/P. (3) WE/P REPORTS IN TEMPLATE FORMAT ARE DUE TO RESPECTIVE REGIONS NO LATER THAN 18 AUGUST 2008. B. REGIONAL COMMANDERS WILL CONSOLIDATE THEIR OWN ASSESSMENT WITH THAT OF THE WE/P AND PROVIDE A SINGLE REGION-WIDE PRELIMINARY EXCESS REPORT TO CNIC POC BY 22 SEPTEMBER 2008. C. CNIC WILL VALIDATE AND INTEGRATE THE WE/P REQUIREMENTS AND EXCESSES BEFORE SUBMITTING A FINAL EXCESS REPORT TO CNO N4. D. CNIC WILL LOOK ACROSS THE TOTALITY OF A LARGER FRAMEWORK (INSTALLATION, REGIONAL, OR NAVY WIDE) IN ASSESSING HOW TO MEET SHORE FACILITY REQUIREMENTS OF BEST VALUE TO THE NAVY, AND REDUCE OUR SHORE INFRASTRUCTURE/FOOTPRINT. 4. ADDITIONAL GUIDANCE WITH REFERENCE TO OTHER ELEMENTS OF REF A FORTHCOMING. 5. RELEASED BY VICE ADMIRAL J. C. HARVEY, JR., DIRECTOR, NAVY STAFF.// BT #0000 NNNN